Arsenal House. June
13.06.2025
In section 1, vertical elements are being installed at the level of the 15th floor. Work has begun on brickwork at the level of the 7th floor.
In section 2, vertical elements of the 13th floor are being installed. Brickwork is underway at the level of the 10th floor.
In section 3, monolithic works and brickwork on residential floors are completed.