Arsenal House. April
18.04.2025

In section 1, the floor slabs above the 16th floor are being constructed. Brickwork is being completed at the 7th floor level.

In section 2, the brickwork at the 10th floor level is complete. Preparations are underway for brickwork at the 11th floor level.

In section 3, the sewer risers from floors 3 to 7 have been installed.

Risers for electrical networks have been completed - all sections.

External networks - engineering network inputs have been completed (sewerage, water supply, heat supply).