Arsenal House. November
27.11.2024

In section 1, vertical elements are being made at the 13th floor level.

In section 2, the 11th floor floor slab is being poured. Brickwork has begun at the 9th floor level.

In section 3, monolithic works have been completed. Brickwork has been completed from the 3rd to the 7th floors.

View the photo report

   