Arsenal House. September
27.09.2024
In section 1, monolithic works are being carried out at the 11th floor level.
In section 2, monolithic works are being carried out at the 10th floor level. Bricklaying is being carried out at the 3rd and 4th floor levels.
In section 3, monolithic works are being carried out at the 8th floor level. Bricklaying is being carried out at the 5th and 6th floor levels.