Arsenal House. December
12.01.2024
In section 1, work is being carried out on the arrangement of vertical structures of the 3rd floor.
In section 2, monolithic works are being carried out at the level of the 3rd floor.
In section 3, work is being carried out on the arrangement of the floor slab of the 5th floor.
View the photo report