Zarichnyu. December
04.01.2023
In building 9, facade decoration works have been completed. The entrance group and finishing works on the floors have been completed. Works on the installation and arrangement of engineering systems are being carried out.
In building 8, external insulation and decoration of the facade are being completed.
In building 7, external insulation and decoration of the facade are being continued.
In building 7.1, internal engineering works are being carried out.
Works on landscaping the yard are being carried out.