Zarichnyu. October
01.11.2022
In building 9, the entrance group is being installed and finishing works are being carried out on the floors. Work on the insulation of the facade and the installation of brackets for air conditioners have been completed. Work on the roof is being completed. Work on the installation and installation of engineering systems is being carried out.
In building 8, the external insulation and finishing of the facade is being carried out, work on the installation of brackets for air conditioners is being carried out.
In building 7, the external insulation and finishing of the facade is being carried out, work on the installation of brackets for air conditioners is being carried out.
Landscaping works are being carried out.