Start. October
01.11.2022
Point 1.1 - 1.4. The installation of the contact facade of the 1st floor is being completed. Internal finishing works in common areas are being completed. Testing and programming of elevator equipment is being completed. Electrical installation works and works on engineering systems are being completed.
Point 2.1 - 2.3. The installation of the contact facade is being completed. Internal finishing works in common areas are being performed. Electrical installation works and works on engineering systems are being performed. Work on installing elevator equipment is being carried out
Work on landscaping the inner courtyard is being carried out.