Start. August
31.08.2022

Point 1.1 - 1.4. The installation of the contact facade is being completed. The interior finishing work in public areas is being completed. The testing and programming of the elevator equipment is being carried out. The electrical installation work and work on engineering systems are being completed.

Point 2.1 - 2.3. The installation of the contact facade is being completed. The interior finishing work in public areas is being completed. The electrical installation work and work on engineering systems are being carried out. The installation of elevator equipment is being carried out

The improvement of the courtyard is underway.