Zarichnyu. January
21.01.2022
In buildings 8 and 9, installation of floor-to-floor smoke exhaust and air support valves is underway. Work continues on insulation and decoration of the facade and installation of brackets for air conditioners, arrangement of internal engineering networks and fire alarm networks, installation of aluminum window structures on the first floor.
In building 7, work continues on insulation of the facade and installation of brackets for air conditioners. Internal engineering works and works in common areas are being carried out: decoration of walls and floors, installation of technical and apartment doors. Work has begun on installation of floor-to-floor smoke exhaust and air support valves
In building 7.1, work continues on arrangement of internal engineering networks.
In the parking lot, work is being completed on the arrangement of monolithic reinforced concrete structures and waterproofing of external walls, brickwork. Work is being carried out on the arrangement of the parking lot and work on the arrangement of engineering systems.
Work continues on backfilling for landscaping and installation of external networks of the complex.
   