Salut. January
21.01.2022

In View Tower, the installation of vertical elements of the 25th floor is being carried out, brickwork is being laid at the level of the 21st floor. Installation of window structures and installation of structures for panoramic glazing is being carried out. Finishing work is being carried out in common areas and internal electrical and plumbing work in apartments.

In Front Tower I, work is being carried out on the installation of vertical elements and floor slabs of the 16th floor. Brickwork is being carried out at the levels of the 5th, 6th and 8th-9th floors.

In Front Tower IV, Front Tower V, work is being carried out on the installation of test bushes.

Work is being carried out on the installation of test bushes in the parking lot.

View the photo report

   