Point 1.1, 1.2, 1.3, 1.4: facade and roof decoration, interior decoration in public areas, installation of elevator equipment, laying of internal engineering networks are being completed. In Point 1.4, installation of equipment for individual heating points is being carried out.
Point 2.1, 2.2, 2.3: facade decoration, laying of internal engineering networks, fencing of stairs and cold passages, installation of windows, installation of elevator equipment, decoration of public areas (painting of walls and installation of tiles on the floor) are being completed.
Work on finishing the parking lot and arranging landscaping continues. Work on arranging the roof of the shopping center is being carried out.
Bricklaying and installation of windows in the kindergarten are being completed.