Zarichnyu. December
23.12.2021
In building 9, installation of floor-level smoke exhaust and air supply valves is underway. Work continues on insulation and finishing the facade and installation of brackets for air conditioners, arrangement of internal engineering networks and fire alarm networks. Work has been completed on installing radiators in apartments, installation of apartment doors, technical doors, doors of communication cabinets. Work has begun on installing aluminum window structures on the first floor.
In building 8, interior finishing work is being carried out in common areas (tiles), work on insulation and finishing the facade and installation of brackets for air conditioners, installation of radiators in apartments. Work has been completed on installing apartment doors, technical doors, doors of communication cabinets. Work has begun on installing aluminum window structures on the first floor.
In building 7, work continues on insulation of the facade and installation of brackets for air conditioners. Internal engineering works and works in public areas are being carried out: wall and floor decoration.
In building 7.1, work is being carried out on the arrangement of internal engineering networks.
In the parking lot, work is being completed on the arrangement of monolithic reinforced concrete structures and waterproofing of external walls. Work has begun on the arrangement of the parking lot and work on the arrangement of engineering systems.
Work continues on backfilling for the arrangement of landscaping and the arrangement of external networks of the complex.