Oasis. December
23.12.2021

In Building 1, work is being carried out to install the 25th floor slab. Brickwork is being carried out at the 15th floor level. Installation of staircases on the 22nd floor, installation of ventilation units.

In Building 2, preparatory work is being carried out to develop the pile field, a tower crane is being installed.

View the photo report

   