Oasis. January
21.01.2022
In Building 1, the work on the installation of the 25th floor floor slab is being completed. Brickwork is being carried out at the 16th floor level. Installation of the 22nd floor staircases, installation of ventilation units.
In Building 2, preparatory work is being carried out to reinforce the building's grillage.