23.12.2021

In the View Tower, the installation of the floor slab of the 24th floor has been completed, the installation of the vertical elements of the 25th floor has begun, and the brickwork at the level of the 21st floor has begun. The installation of window structures and arrangement of structures for panoramic glazing is carried out. Finishing works in common areas and internal electrical and plumbing works in apartments are carried out.

In Front Tower I, work is underway on the arrangement of vertical elements and the floor slab of the 16th floor. Brickwork on the 5th, 6th and 8th floors.

In Front Tower IV, Front Tower V, work on the arrangement of test bushes is being carried out.

In the parking lot, work on the arrangement of test bushes is being carried out.