Start. December
23.12.2021

Point 1.1, 1.2, 1.3, 1.4: finishing works on the facade, internal finishing works in common areas (painting of walls and tiling on the floor), installation of elevator equipment, laying of internal engineering networks. In Point 1.4, work continues on the installation of equipment for individual heating points.

Point 2.1, 2.2, 2.3: finishing works on the facade, laying of internal engineering networks, fencing of stairs and cold passages, installation of windows, installation of elevator equipment, decoration of common areas (painting of walls and installation of tiles on the floor) are being completed.

Work on the arrangement of the parking lot, shopping center and landscaping continues.

The bricklaying of the kindergarten is being completed.

   