In buildings 8 and 9, work continues on the insulation and finishing of the facade and installation of brackets for air conditioners, arrangement of internal engineering networks and fire alarm networks, installation of apartment and technical doors, and wall and floor finishing in common areas. Installation of radiators has begun.
Works on facade insulation and installation of brackets for air conditioners continue in building 7. Roofing works are nearing completion. Internal engineering works and works in common areas are underway: wall and floor finishing.
Works on the arrangement of internal engineering networks are underway in the building 7.1.
In the parking lot, work is being completed on the installation of monolithic reinforced concrete structures and waterproofing of external walls. Brickwork is underway. Work has begun on the installation of engineering systems.
Backfilling works are underway for landscaping and installation of external networks of the complex.