Point 1.1, 1.2, 1.3, 1.4: facade finishing works, interior finishing works in common areas, and installation of internal utility networks are being completed. The cold passages have been equipped, and technical and apartment doors have been installed.
Point 2.1, 2.2: facade finishing works, installation of internal utility networks, fencing of stairs and cold passages, installation of windows, installation of elevator equipment, and finishing of common areas are being completed.
Point 2.3: works on facade finishing, laying of utility networks, interior finishing works in common areas, installation of elevator equipment, windows, fencing of stairs and cold passages are ongoing. Brickwork at the level of the 25th floor.
Work continues on the parking lot, shopping center and landscaping.
The installation of vertical elements on the 2nd floor of the kindergarten has been completed.