Oasis. July
30.07.2021

Work is underway on the installation of vertical elements, floor slabs and support columns at the level of the 14th floor.

The brickwork on the 6th floor has been completed. Work has begun on the brickwork on the 7th floor.

Installation of staircases from the 11th to the 13th floors, installation of ventilation units.