Zarichnyu. July
30.07.2021

Works on facade insulation and installation of air conditioning brackets are underway in buildings 8 and 9. The arrangement of internal engineering networks and finishing of common areas continues. Elevators are being installed.

Works on facade insulation and installation of brackets for air conditioners are underway in building 7. Installation of window structures and roofing is nearing completion. Internal engineering networks are being laid. Elevators are being installed.

The floor slab of the 3rd floor has been completed in building 7.1. Work is underway to install vertical structures on the 4th floor. 

Work is underway on the installation of monolithic reinforced concrete structures and waterproofing of the external walls of the parking lot.